CHIEF ENGINEER/THERMAL DESIGNS
There are Five Directorates and One Accounts Office alongwith Works Section under the Admn. of
CE/Thermal Designs. The classification of work under each Directorate is as under: -
ELECTRICAL DIRECTORATE
To deal with the Main Electrical Equipment of GHTP Stage-II i.e. Turbine & Generator, Switch Yard
Control & Instrumentation (C&I), Transformers, Switchgears, Breakers, Isolators, Cabling, lighting etc.
MECHANICAL DIRECTORATE
Mainly to deal with Boiler its Auxiliaries and other allied works like Coal Handling Plant (CHP), Ash Handling
Plant (AHP), DM Plant, L.P. Piping, H.P. Piping, Fire Fighting & Protection Systems & Handling of Fly Ash etc.
CIVIL DIRECTORATE
To deal with Cooling Tower, Chimney, Ash Dykes, Raw Water System, Main Plant and other foundations &
piling etc.
PROJECT DIRECTORATE
To deal with the finalization of new thermal plants .
FLY ASH DIRECTORATE
To deal with the utilisation of Dry Fly Ash concerned with the three projects i.e. GNDTP Bathinda, GGSSTP
Ropar & GHTP Lehra Mohabbat.
ACCOUNTS OFFICE
To deal with the firms in respect of their payments and advance, besides financial aspects.
of Esstt. with different heads.
WORKS SECTION
This is an integrated part of Chief Engineer Office to assist for compiling information received from
all Directorates of Thermal designs as well as from Site Offices & administrative matters.
Annexure-A
1) |
Name of the Project |
Guru Hargobind Thermal Plant Stage-II |
2) |
Location |
Lehra Mohabbat, Distt. Bathinda |
3) |
Installed Capacity unit wise |
2 x 250 = 500 MW |
4) |
Type of Fuel |
Coal |
5) |
Executing Agency |
BHEL |
6) |
Clearances Status |
Cleared by CEA, New Delhi. Investment approved by Planning Commission. All clearance obtained. |
7) |
Total estimated Cost |
Rs. 2123 Crores (approx.) |
8) |
Synchronization dates |
Unit-3 Commercial Operation Date (COD) 16-10-08 |
9) |
Annual Generation at 68.5% load factor |
3000 MU 2715 MU Net |
10) |
Coal consumption / year |
1860000 Ton |
11) |
Cost of Generation |
Rs. 3.17 (at Bus Bar). |
12) |
Latest Status |
Order is placed on turnkey/EPC basis on BHEL on 31.03.04. Unit -3 COD 16-10-08. |
|